Wallboard to be replaced in the master bedroom to the left of the window and below

    Details

    • Type: Wallboards/Ceiling Boards (8 Weeks) Wallboards/Ceiling Boards (8 Weeks)
    • Status: Complete
    • Priority: High High
    • Resolution: Completed
    • Labels:
      None
    • ID Number:
      SBH002970
    • Model:
      Bordeaux 2012
    • Serial:
      unknown
    • Size:
      38x12
    • Part Number:
      1711522
    • Status Colour:
      Complete Complete
    • Supplier:
      Swift
    • Park_Company:
       Not defined
    • Additional Contact Details:
      Rob
    • SLA Status:
    1. quot-1314.docx
      14 kB
      Adrienne Barwell
    1. CCF07082014_00000.jpg
      788 kB
    2. CCF07082014_00001.jpg
      312 kB
    3. CCF22072014_00000.jpg
      648 kB
    4. screenshot-1.jpg
      225 kB
    5. screenshot-2.jpg
      256 kB
    6. screenshot-3.jpg
      217 kB
    7. screenshot-4.jpg
      189 kB
    8. screenshot-5.jpg
      209 kB

      Issue Links

        Activity

        Hide
        Adrienne Barwell (Inactive) added a comment -
        quote supplied. awaiting response
        Show
        Adrienne Barwell (Inactive) added a comment - quote supplied. awaiting response
        Hide
        Claire Folland added a comment -
        received wallboard delivery note 76471
        Show
        Claire Folland added a comment - received wallboard delivery note 76471
        Hide
        Ellie W (Inactive) added a comment -
        Worksheet attached - this work was completed however engineer was asked by Rob (salesman) to compete the following job:
        LV2 Atlas Lilac, fir skirting for the second bedroom, remove the radiator, drawer unit and 1 wall board as insulation is required.
        Show
        Ellie W (Inactive) added a comment - Worksheet attached - this work was completed however engineer was asked by Rob (salesman) to compete the following job: LV2 Atlas Lilac, fir skirting for the second bedroom, remove the radiator, drawer unit and 1 wall board as insulation is required.
        Hide
        Adrienne Barwell (Inactive) added a comment -
        Steve was only on site for 15 minutes so could not have completed the job. Site are chasing to find out when he will be attending
        Show
        Adrienne Barwell (Inactive) added a comment - Steve was only on site for 15 minutes so could not have completed the job. Site are chasing to find out when he will be attending

          People

          • Assignee:
            Maureen Hooper (Inactive)
            Reporter:
            Adrienne Barwell (Inactive)
          • Watchers:
            1 Start watching this issue

            Dates

            • Due:
              Created:
              Updated:
              Resolved:
              Parts in:
              Work Scheduled: