PDI reports holes above cabinet in main bathroom

    Details

    • Type: Wallboards/Ceiling Boards (8 Weeks) Wallboards/Ceiling Boards (8 Weeks)
    • Status: Complete
    • Priority: Agreed Date Agreed Date
    • Resolution: Completed
    • Labels:
      None
    • Responsibility:
      Manufacturer Attending
    • Serial:
      019597h
    • Manufacturer:
      Swift
    • Model:
      Loire
    • Year:
      2016
    • Size:
      35x12
    • ID Number:
      SBH004901
    • Status Colour:
      Complete Complete
    • Stock_Number:
      31644
    • Times Scheduled:
      1
    • Park_Company:
       Surf Bay Leisure (Winkleigh)
    • Park_Postcode:
      EX19 8DW
    • Park_Phone:
      01837 680100
    • Park_Email:
      warranty@surfbay.co.uk
    • Park_Code:
      SURF99
    • Park_Key_Account:
      No
    • SLA Status:

      Activity

      Nikki Milling (Inactive) created issue -
      Nikki Milling (Inactive) made changes -
      Field Original Value New Value
      Project PDI [ 10950 ] Swift [ 10018 ]
      Key PDI-1025 SWIFT-9100
      Issue Type PDI (2 weeks) [ 15 ] Wallboards/Ceiling Boards (8 Weeks) [ 6 ]
      Workflow PDI: Simple Issue Tracking Workflow [ 169121 ] Manufacturers ver 2.2 [ 169122 ]
      Responsibility Undecided [ 10040 ]
      Depot Winkleigh [ 12050 ]
      Times Scheduled 0
      Nikki Milling (Inactive) made changes -
      Due Date 21/Sep/15 19/Nov/15
      Nikki Milling (Inactive) made changes -
      Status Open [ 1 ] Submitted [ 10001 ]
      Hide
      Nikki Milling (Inactive) added a comment -
      Reported via PDI and submitted to swift.
      Show
      Nikki Milling (Inactive) added a comment - Reported via PDI and submitted to swift.
      Nikki Milling (Inactive) made changes -
      ID Number SBH004901
      Adrienne Barwell (Inactive) made changes -
      Status Submitted [ 10001 ] Acknowledged [ 10005 ]
      Responsibility Undecided [ 10040 ] Manufacturer Attending [ 10045 ]
      Manufacturer Swift
      Hide
      Adrienne Barwell (Inactive) added a comment -
      Swift have confirmed that they will be attending
      Show
      Adrienne Barwell (Inactive) added a comment - Swift have confirmed that they will be attending
      Adrienne Barwell (Inactive) made changes -
      Attachment screenshot-1.jpg [ 101848 ]
      Adrienne Barwell (Inactive) made changes -
      Assignee Nikki Milling [ nikkim ] Adrienne Barwell [ adrienne ]
      Adrienne Barwell (Inactive) made changes -
      Status Acknowledged [ 10005 ] Worksheet Issued [ 10004 ]
      Adrienne Barwell (Inactive) made changes -
      Times Scheduled 0 1
      Status Worksheet Issued [ 10004 ] Engineer Scheduled [ 10000 ]
      Work Scheduled 05/Oct/15
      Plot
      Adrienne Barwell (Inactive) made changes -
      Priority Normal [ 21 ] Agreed Date [ 26 ]
      Adrienne Barwell (Inactive) made changes -
      Attachment screenshot-2.jpg [ 101849 ]
      Hide
      Adrienne Barwell (Inactive) added a comment -
      Swift have advised that they will be attending w/c 5/10/15
      Show
      Adrienne Barwell (Inactive) added a comment - Swift have advised that they will be attending w/c 5/10/15
      Hide
      Adrienne Barwell (Inactive) added a comment -
      Swift have advised that this issue has been rejected.
      Show
      Adrienne Barwell (Inactive) added a comment - Swift have advised that this issue has been rejected.
      Hide
      Adrienne Barwell (Inactive) added a comment -
      I have checked the Swift Loire's in the yard and they all have holes above the bathroom mirror/cabinet, this is where they feed the electrical wires through to the unit. The whole on this one is slightly bigger than the other units. It is not something that can be seen, however, it would be noticeable if someone put there hand up there. It has been rejected by Swift as standard.

      I will close this issue and see if anything is mentioned when the unit is sold.
      Show
      Adrienne Barwell (Inactive) added a comment - I have checked the Swift Loire's in the yard and they all have holes above the bathroom mirror/cabinet, this is where they feed the electrical wires through to the unit. The whole on this one is slightly bigger than the other units. It is not something that can be seen, however, it would be noticeable if someone put there hand up there. It has been rejected by Swift as standard. I will close this issue and see if anything is mentioned when the unit is sold.
      Adrienne Barwell (Inactive) made changes -
      Status Engineer Scheduled [ 10000 ] Issue Invoice [ 10451 ]
      Assignee Adrienne Barwell [ adrienne ] Ellie W [ temp ]
      Adrienne Barwell (Inactive) made changes -
      Status Issue Invoice [ 10451 ] Awaiting Payment [ 10151 ]
      Adrienne Barwell (Inactive) made changes -
      Status Awaiting Payment [ 10151 ] Resolved [ 5 ]
      Assignee Ellie W [ temp ] Adrienne Barwell [ adrienne ]
      Adrienne Barwell (Inactive) made changes -
      Status Resolved [ 5 ] Complete [ 6 ]
      Adrienne Barwell (Inactive) made changes -
      Status Complete [ 6 ] Reopened [ 4 ]
      Adrienne Barwell (Inactive) made changes -
      Status Reopened [ 4 ] Resolved [ 5 ]
      Resolution Completed [ 1 ]
      Adrienne Barwell (Inactive) made changes -
      Status Resolved [ 5 ] Complete [ 6 ]
      made changes -
      Park_Contact
      Transition Time In Source Status Execution Times Last Executer Last Execution Date
      Open Open Submitted Submitted
      4m 10s 1 Nikki Milling (Inactive) 10/Sep/15 8:37 AM
      Submitted Submitted Acknowledged Acknowledged
      7d 8h 17m 1 Adrienne Barwell (Inactive) 17/Sep/15 4:55 PM
      Acknowledged Acknowledged Worksheet Issued Worksheet Issued
      5d 22h 9m 1 Adrienne Barwell (Inactive) 23/Sep/15 3:04 PM
      Worksheet Issued Worksheet Issued Engineer Scheduled Engineer Scheduled
      9s 1 Adrienne Barwell (Inactive) 23/Sep/15 3:04 PM
      Engineer Scheduled Engineer Scheduled Issue Invoice Issue Invoice
      20h 34m 1 Adrienne Barwell (Inactive) 24/Sep/15 11:38 AM
      Issue Invoice Issue Invoice Awaiting Payment Awaiting Payment
      4s 1 Adrienne Barwell (Inactive) 24/Sep/15 11:38 AM
      Awaiting Payment Awaiting Payment Resolved Resolved
      3s 1 Adrienne Barwell (Inactive) 24/Sep/15 11:38 AM
      Complete Complete Reopened Reopened
      4h 2m 1 Adrienne Barwell (Inactive) 24/Sep/15 3:41 PM
      Reopened Reopened Resolved Resolved
      5s 1 Adrienne Barwell (Inactive) 24/Sep/15 3:41 PM
      Resolved Resolved Complete Complete
      9s 2 Adrienne Barwell (Inactive) 24/Sep/15 3:41 PM